Norway: Long-term outage for Hammerfest LNG


26 Oct 2020

Photo - see caption

Surveys of the damage after the fire at Hammerfest LNG on 28 September indicates that the LNG plant will be closed for up to 12 months for repairs.

In addition to damage caused by the fire on the air intake on one of the plant's five power turbines, large amounts of seawater from the extinguishing have damaged other auxiliary systems such as electrical equipment and cables in the plant.

It is the scope of work of this consequential damage that are considered the most extensive and the duration of the shutdown will depend on the delivery time of necessary equipment. Progress will also be affected by the current restrictions related to the Covid 19 virus.

Photo - see caption
Long-term outage for Hammerfest LNG

The Hammerfest LNG plant. (Photo: Helge Hansen / Equinor ASA)

'Safety is the first priority and we will not start the plant until we are sure that it can be done in a safe way. Therefore, we have worked systematically and thoroughly to survey the damage after the fire, and assess the technical condition of the plant,' says plant director Andreas Sandvik.

'Although a lot of inspection work still remains and there is still significant uncertainty, our best estimate now is that that it may take up until 1 October 2021 to get Hammerfest LNG back into production.'

'We will use the shutdown period to also carry out other maintenance and repair work planned for 2021. This includes both ongoing maintenance and maintenance planned in a planned turnaround next spring,' Sandvik says.

Equinor, as well as the PSA and the police have started independent investigations of the fire.

'The fire at Hammerfest LNG was a serious incident. The various investigations into the incident will be important in order to identify measures that will prevent similar incidents from happening again,' says Grete B. Haaland, senior vice president for Equinor's onshore facilities.

Original article link

Source: Equinor





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 373

Completed Deals

Completed Upstream Deals: 5961

Company Profiles

Current Company Profiles: 2745

Corporate Activity

Current Corporate Activity articles: 3564

Companies Looking

Current number of articles: 444

Company Sales

Current Company Sales articles:1443

Geostudies

Current Geostudies articles: 766

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

SLR Consulting logo
Government of South Australia
Rose & Assocs 149
Bayphase
Union Jack Oil 149
OPC
KL Publishing
energy365
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com