Botswana: Tlou Energy announces operational report - quarter ended 30 June 2023


25 Jul 2023

Photo - see caption

Highlights

  • Lesedi 6 production pod drilling completed
  • The 66kV overhead transmission line is approximately 79% complete
  • At the quarter end the Company had ~A$6.85m cash on hand (unaudited)
Photo - see caption

Activities

Tlou Energy continues to have three key project areas referred to as the:

  • Lesedi Project - focused on gas-to-power development as well as exploration and evaluation.
  • Mamba Project - focused on exploration and evaluation.
  • Boomslang Project - focused on exploration and evaluation.

Lesedi Project

The Lesedi project is Tlou's most advanced. At Lesedi the Company is developing a proposed 10MW gas-to-power project. The Lesedi project area has four Prospecting Licenses (PL) and a Production Licence which is the key focus area for the development of Tlou's independently certified gas reserves and contingent resources. The table below summarises the status of the Lesedi licences:

Photo - see caption

PL renewal applications are submitted three months prior to expiration. Renewal applications were submitted for PL001/2004 and PL003/2004 during the quarter.

Gas to Power Project

The first electricity to be generated at Lesedi is planned to go towards satisfying the 10MW Power Purchase Agreement (PPA) with Botswana Power Corporation (BPC) the national power utility. The Lesedi project currently has several components of the development process underway including the construction of transmission lines, substations, a field operations facility and generation site as well as production well drilling.

Transmission Line Construction

The Lesedi project is approximately 100km from the nearest BPC substation connection in Serowe. To connect to the national grid, the Company is undertaking the construction and installation of a 100km 66kV transmission line. This, together with the ongoing drilling program should enable the Company to connect and provide electricity into Botswana's power network.

The construction of the 66kV transmission line is being carried out by Zismo Engineering Pty Ltd with progress at the end of June 2023 estimated at approximately 79%. The expected July 2023 completion date has been pushed back due to a delay in availability of line conductors as well as hard rock excavation and the discovery of previously unknown sub-surface services with has slowed progress. However, the transmission line construction remains on target to be completed well in advance of proposed first power generation.

Substation Construction

Substations are required at either end of the transmission line, one to tie Tlou's generators to the transmission line at Lesedi and another to integrate the line with the existing BPC substation at Serowe. The planned substation at Lesedi is currently designed for an initial 5MW of power which can be upgraded to 10MW at a later stage with the project anticipated to be completed in early 2024. The Company is now assessing options that may allow the current substation design to be adapted to facilitate expansion beyond 10MW.

Drilling Operations

During the quarter the Company began drilling the latest production pod, Lesedi 6, the first of a series of new pods (funds permitting) that the Company plans to drill as part of the 10MW gas to power project. Lesedi 6 comprises one vertical production well (Lesedi 6P) intersected by two lateral wells (Lesedi 6A and 6B) drilled horizontally through the target reservoir section for several hundred metres.

Lesedi 6P - Vertical Production Well

This well was drilled to a depth of 589m and intersected 6m of the target lower Morupule coal. Well casing was cemented in place, with fiberglass casing over the target coal seam underreamed to expose the coal to the well bore to facilitate dewatering and gas flow.

Lesedi 6A and Lesedi 6B - Lateral Wells

The top hole (or vertical) sections of Lesedi 6A and Lesedi 6B were drilled during the quarter. Both were drilled to a depth of 150m and cased with steel casing and cemented. Following cementing, the wells were deepened in preparation for running the directional tools which are required to complete the lateral section of the well. Drilling of the lateral sections commenced thereafter with both lateral sections successfully intersecting Lesedi 6P post quarter end.

Photo - see caption

Core-hole drilling

In addition to the Lesedi 6 production pod, a core-hole was drilled close to the vertical sections of Lesedi 6A and 6B. The objective of the core-hole was to provide further geological control. In addition to providing coal and gas content data, the core-hole accurately determined the top and bottom of the target coal seam. The core-hole was completed and logged after reaching a total depth of 535m and intersecting 6m of coal. A total of 18 coal samples were taken and placed in desorption canisters for further analysis.

A further core-hole was commenced prior to quarter end which was located close to where another new production pod (Lesedi 7) is proposed to be drilled at a later date.

Mamba Project

The Mamba project is in the exploration and evaluation phase with further operations required on the operating licences. It consists of five Prospecting Licences covering an area of approximately 4,500 Km2. The Mamba area is situated adjacent to Lesedi. In the event of successful drilling results at Mamba, it is envisioned that this area would be developed as a separate project from Lesedi. The Mamba area provides the Company with flexibility and optionality. The status of the Mamba licences is as follows:

Photo - see caption

PL renewal applications are submitted three months prior to expiration. Renewal applications for all Mamba project licences were submitted during the quarter.

Boomslang Project

Prospecting Licence, PL011/2019 designated "Boomslang", is approximately 1,000 Km2 and is situated adjacent to the Company's existing licences. To date, the Company has not carried out ground operations in the Boomslang area. The status of the Boomslang licence is as follows:

Photo - see caption

PL renewal applications are submitted three months prior to expiration.

Cash Position

At the end of the quarter the Company had ~A$6.85m cash on hand (unaudited). The aggregate value of payments to related parties and their associates of A$235k for the quarter (shown in item 6.1 of the attached Quarterly Cashflow Report) relates to directors' salaries and fees (including tax and superannuation payments made on their behalf) and office rent.

Original article link

Source: Tlou Energy





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2933

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Bayphase
energy365
Rose & Assocs
OPC
Borchwix
Syntillica
Union Jack Oil 149
Telos NRG
Merlin
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com