News listings

energy-pedia development and production

Botswana flagBotswana

Middle East / Africa >>> Botswana

Botswana: Tlou Energy announces quarterly activity report q/e 30 September 2023


27 Oct 2023

Photo - see caption

Tlou Energy, developing power solutions for Botswana through gas-fired power and ancillary projects, has announced a quarterly activity report on its Lesedi, Mamba and Boomslang Projects.

Highlights

  • Lesedi 6 production pod and the redrill of Lesedi 4 lateral wells completed successfully
  • The 66kV overhead transmission line is ~94% complete
  • Work on the electrical substations is ~36% complete

Map Description automatically generated

Activities

Tlou Energy has three project areas referred to as the:

  • Lesedi Project - focused on gas-to-power development as well as exploration and evaluation.
  • Mamba Project - focused on exploration and evaluation.
  • Boomslang Project - focused on exploration and evaluation.

Lesedi Project

The Lesedi project is Tlou's most advanced. At Lesedi the Company is developing a proposed 10MW gas-to-power project. The project area has four Prospecting Licenses (PL) and a Production Licence which is the focus area for the development of Tlou's independently certified gas reserves and contingent resources. The table below summarises the status of the Lesedi licences:

Licence

Expiry

Status

Production Licence 2017/18L

Aug-42

Current

PL001/2004

Sep-23

Awaiting renewal confirmation

PL003/2004

Sep-23

Awaiting renewal confirmation

PL035/2000

Mar-25

Current

PL037/2000

Mar-25

Current

PL renewal applications are submitted three months prior to expiration. Renewal applications were submitted for PL001/2004 and PL003/2004 in June 2023 and the Company is awaiting confirmation of renewal.

Gas to Power Project

The first electricity to be generated at Lesedi is planned to go towards satisfying the 10MW Power Purchase Agreement (PPA) with Botswana Power Corporation (BPC) the national power utility. The Lesedi project currently has several components of the development process underway including the construction of transmission lines, substations, a field operations facility and generation site as well as production well drilling.

Transmission Line Construction

The Lesedi project is approximately 100km from the nearest BPC substation connection in Serowe. To connect to the national grid, the Company is undertaking the construction and installation of a 100km 66kV transmission line. This, together with the ongoing drilling program should enable the Company to connect and provide electricity into Botswana's power network.

The construction of the 66kV transmission line is being carried out by Zismo Engineering Pty Ltd (Zismo). Completion of the line is currently expected to be around December 2023. The major outstanding items are the manufacture of the remaining steel poles, a road crossing and the relocation of an 11kV line that was constructed across Tlou's wayleave. Thereafter the line should be ready to be energised once the terminal substation works are completed and commissioned. Tlou Energy will not take ownership of the line until the substation work is complete and the line can be energised. Zismo's contract will therefore need to be extended for care and maintenance of the line until it is taken over upon energisation.

Substation Construction

Substations are required at either end of the transmission line, one to tie Tlou's generators to the transmission line at Lesedi and another to integrate the line with the existing BPC substation at Serowe. The planned substation at Lesedi is currently designed for an initial 5MW of power which can be upgraded to 10MW at a later stage with the project anticipated to be completed in early 2024. The Company is assessing options that may allow the current substation design to be adapted to facilitate expansion beyond 10MW.

The substation contract was placed with Optipower earlier this year. Optipower appointed SMEC as a sub-contractor for detailed engineering design and Makgarapa for civil engineering construction works. Makgarapa also completed the sites' geotech assessments, soil resistivity and topographical surveys. SMEC have produced the design schedule. Optipower has completed site establishment at both Serowe and Lesedi.

Drilling Operations

During the quarter the Company completed a redrill of both lateral wells of the Lesedi 4 production pod. The aim of redrilling the lateral wells was to provide straighter lateral sections using a specialist rotary steerable system (RSS).  The lateral sections were drilled for approximately 700m and successfully intersected with the Lesedi 4P vertical production well. These straighter laterals are expected to assist with removing water from the reservoir to more efficiently dewater and flow gas.

In addition, drilling of a new production pod, Lesedi 6, was completed during the quarter. The RSS was also used for the lateral sections of this production pod. Post drilling, both Lesedi 4 and Lesedi 6 pods were flushed to clear the wells and have had production equipment installed to commence dewatering ahead of gas production.

A diagram of a well Description automatically generated with low confidence

 


 

 

****

 

 

 

 

 

 

Mamba Project

The Mamba project is in the exploration and evaluation phase with further operations required on the licences. It consists of five Prospecting Licences covering an area of approximately 4,500 Km2. The Mamba area is situated adjacent to Lesedi. In the event of successful drilling results at Mamba, it is envisioned that this area would be developed as a separate project from Lesedi. The Mamba area provides the Company with flexibility and optionality. The status of the Mamba licences is as follows:

Licence

Expiry

Status

PL 237/2014

September 2023

Awaiting renewal confirmation

PL 238/2014

September 2023

Awaiting renewal confirmation

PL 239/2014

September 2023

Awaiting renewal confirmation

PL 240/2014

September 2023

Awaiting renewal confirmation

PL 241/2014

September 2023

Awaiting renewal confirmation

PL renewal applications are submitted three months prior to expiration. Renewal applications for all Mamba project licences were submitted in June 2023 and the Company is awaiting confirmation of renewal. Further work on the Mamba project is proposed once the Lesedi project is in production. The next stage of operations is likely to include a seismic survey and the drilling of core-holes.

Boomslang Project

Prospecting Licence, PL011/2019 designated 'Boomslang', is approximately 1,000 Km2 and is situated adjacent to the Company's existing licences. To date, the Company has not carried out ground operations in the Boomslang area. Like the Mamba project the first stage of operations is likely to include a seismic survey following by core-hole drilling.

The status of the Boomslang licence is as follows:

Licence

Expiry

Status

PL 011/2019

June 2024

Current

PL renewal applications are submitted three months prior to expiration.

Cash Position

At the end of the quarter the Company had ~A$1.87m cash on hand (unaudited). The aggregate value of payments to related parties and their associates of A$267k for the quarter (shown in item 6.1 of the Quarterly Cashflow Report appended below) relates to directors' salaries and fees (including tax and superannuation payments made on their behalf) and office rent. The Company will need to raise additional funds in the next quarter and the steps being taken to do so are set out in item 8.8 of the Quarterly Cashflow Report.

Original announcement link

Source: Tlou Energy





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 237

Completed Deals

Completed Upstream Deals: 6558

Company Profiles

Current Company Profiles: 2912

Corporate Activity

Current Corporate Activity articles: 4136

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1653

Geostudies

Current Geostudies articles: 964

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Borchwix
Bayphase
energy365
Government of South Australia
Syntillica
Telos NRG
OPC
Union Jack Oil 149
Rose & Assocs
Merlin
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com