Congo (Brazzaville): PetroNor E&P provides Q2 2024 production update


10 Jul 2024

Photo - see caption

PetroNor E&P has provided an update on the Congo operations related to the PNGF Sud field complex.

Second quarter average net working interest production was 4,672* bopd, compared with 5,037 bopd in the previous quarter and 5,003 bopd in the same period in 2023. Production efficiency during the quarter averaged 81 per cent, which is lower than the 2023 average of 92 per cent, due to system instabilities from commissioning activities and third-party power import interruptions. These instabilities have also contributed to a growing number of workover candidates. In order to address this backlog an additional workover team has been added to bring the number of teams assigned to PNGF Sud up to three. The third team is expected to start during July.

Photo - see caption

Commissioning of the new Tchendo 2 platform was completed in April, and the generators produce some 10MW power to the wider field. Power generation is currently fuelled with gas from the nearby Likouala field, operated by Congorep (Perenco has a 35 per cent interest). A new gas line from Tchibeli NE, Tchibeli and Litanzi to Tchendo 2 will be finished mid-July to allow the PNGF Sud to be self-sufficient for its power needs.

With stable power supply and three operational workover crews, production rates and production efficiencies are forecasted to increase in the second half of the year. With normalised production efficiencies, the production capacity of the field and wells would be 5,300 bopd on a net basis.

As communicated previously, the Company has lifted and sold 914,268 bbls of oil for an average realised price of USD 82.70 per barrel year-to-date. The next lifting is scheduled for the fourth quarter.

The full account of production (including final allocation) will be presented in the interim report for the second quarter of 2024.

*Final (net to PetroNor 16.83 per cent) production allocation for the month of April, preliminary production allocation for May and June.

Original announcement link

Source: PetroNor





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 213

Completed Deals

Completed Upstream Deals: 6617

Company Profiles

Current Company Profiles: 2923

Corporate Activity

Current Corporate Activity articles: 4181

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1671

Geostudies

Current Geostudies articles: 994

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Telos NRG
Syntillica
OPC
Merlin
Borchwix
energy365
Rose & Assocs
Union Jack Oil 149
Government of South Australia
Bayphase
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com