News listings

energy-pedia general news

Woodside announces third quarter report for period ended 30 September 2023


18 Oct 2023

Photo - see caption

Delivering reliable production

  • Delivered quarterly production of 47.8 MMboe (520 Mboe/day), up 8% from Q2 2023 following completion of planned turnaround and maintenance activities. Full-year production guidance has been narrowed to 183 – 188 MMboe.
  • Delivered sales volume of 53.3 MMboe, up 10% from Q2 2023, primarily due to higher production.
  • Delivered revenue of $3,259 million, up 6% from Q2 2023, due to higher production offset by lower realised prices.
  • Achieved a portfolio average realised price of $60.2/boe.
  • Sold 29% of produced LNG at prices linked to gas hub indices.
  • Achieved first production at Shenzi North in September 2023, ahead of the 2024 target.

Executing major projects

  • The Scarborough and Pluto Train 2 project was 46% complete at the end of the period, with fabrication of the floating production unit (FPU) and Pluto Train 2 modules progressing.
  • The Sangomar project was 90% complete at the end of the period, with 14 of 23 wells drilled and completed. The floating production storage and offloading (FPSO) topsides integration and pre-commissioning works continued in Singapore.
  • The Trion field development plan (FDP) was approved by the Mexican regulator, with the project now moving into execution phase.

Carbon and new energy

  • The H2OK final investment decision (FID) has been delayed pending more certainty regarding Government tax incentive qualifications and customer offtake agreements.
  • Substantially completed installation works within Pluto LNG and progressed commercial agreements including solar farm and battery energy storage system agreements to support Woodside Solar targeted FID readiness of 2023.

Woodside CEO Meg O’Neill said the quarter-on-quarter increase in output to 47.8 million barrels of oil equivalent was underpinned by strong operating results at Pluto LNG.

'The 99.9% reliability achieved at Pluto during the third quarter followed the completion of a maintenance turnaround in June.

'Production from North West Shelf was impacted by planned turnaround and maintenance activities in the quarter, but the facility’s reliability was still exceptional at 98.9%.

'Woodside’s project teams made strong progress over the course of the quarter.

'In September, first production at the Shenzi North tieback in the US Gulf of Mexico was achieved ahead of the original 2024 schedule. Production at Mad Dog Phase 2 offshore Louisiana, which started up in April, continued to ramp up during the quarter.

'Activity at Scarborough and Pluto Train 2 increased as planned and the project is now 46% complete. Installation of the nearshore component of the Scarborough trunkline commenced and fabrication of the floating production unit topsides and hull continued.

'Site construction works for Pluto Train 2 are progressing and we have awarded the engineering, procurement and construction contract for the Pluto Train 1 modifications that will allow it to process Scarborough gas.

'The Federal Court’s 28 September decision that the Commonwealth Environment Plan for the Scarborough offshore seismic survey is invalid has not impacted our target for first LNG cargo in 2026. The decision does however highlight the urgent need for reform of Australia’s offshore approvals process.

'Uncertainty over approvals has the potential to add cost and delays to any offshore activities to be undertaken in Australia. In the case of gas projects, such uncertainty threatens the delivery of much-needed new supplies to the Western Australian domestic market, as well as undermining the confidence of our regional trading partners.

'The importance of Scarborough to regional energy security was demonstrated in August when LNG Japan agreed to purchase a 10% non-participating interest in the joint venture.

'As part of a broader strategic relationship, Woodside and LNG Japan, owned by Sumitomo Corporation and Sojitz Corporation also entered into a non-binding heads of agreement for the sale and purchase of approximately 0.9 million tonnes per annum of LNG for 10 years commencing in 2026. In addition, we entered
into non-binding agreements with Sumitomo and Sojitz to collaborate on new energy opportunities globally.

'At Sangomar in Senegal, another two of the 23 planned wells were drilled, taking the total now completed to 14. Pre-commissioning work at the floating production storage and offloading vessel continued in Singapore. Overall, the Sangomar project is 90% complete and we remain on track for targeted first oil in mid-2024.

'A significant milestone for our deepwater Trion project was passed during the quarter, with the approval of the field development plan by the Mexican regulator. Project execution activities at Trion are progressing.

'In new energy, progress was made on contracts for the plant construction scope and other critical packages at our proposed H2OK facility in Oklahoma. Technical work to support readiness for a final investment decision at H2OK is expected to be completed in 2023, although a decision itself has been delayed, pending clarification of government tax incentives and the finalisation of offtake agreements.

'During the quarter we signed two non-binding memoranda of understanding with a total of four Japanese companies to jointly study potential carbon capture and storage (CCS) value chains between Australia and Japan. We believe that with collaboration between industry partners and governments CCS could provide a pathway to help our Japanese customers decarbonise,' she said.

Original announcement link

Source: Woodside





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 236

Completed Deals

Completed Upstream Deals: 6565

Company Profiles

Current Company Profiles: 2912

Corporate Activity

Current Corporate Activity articles: 4143

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1656

Geostudies

Current Geostudies articles: 966

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Merlin
energy365
Bayphase
OPC
Syntillica
Union Jack Oil 149
Government of South Australia
Telos NRG
Rose & Assocs
Borchwix
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com