Highlights
- Podere Maiar - 1 has successfully obtained all final approvals for gas production
- Completion of safety checks by UNMIG and Fire Department
- Italian Energy Ministry (MASE) issue final approval
- The slickline unit has commenced performing well work activities
- Gas production at PM-1 is set to commence in early July 2023
Prospex Energy, the AIM quoted investment company focused on European gas and power projects, has announced that the final safety checks conducted by UNMIG and the local Fire Department on the gas facility at the Po Valley Energy-operated Selva field in the Po Valley region of northern Italy have been successfully completed. Additionally, the Italian Energy Ministry, The Ministry of Environment and Energy Security ('MASE') has issued formal documentation, enabling the commencement of production from the Podere Maiar-1 ('PM-1') gas facility at the Selva field.
Now that MASE has signed and issued the final approval documentation, a mandatory 8-day period is required to finalise all administrative matters before production can begin. Therefore, the operator of the Selva Malvezzi production concession, Po Valley Operations Pty Limited anticipates that the gas production ramp-up at PM-1 will commence in early July 2023.
A slickline unit has been mobilised to the well site and has commenced the necessary activities to allow gas production to start.
The Company will provide further market updates once production has commenced.
Po Valley Operations Pty Limited, a wholly owned subsidiary of Po Valley Energy Limited, is the Operator of the Selva Malvezzi production concession with a 63% working interest, while Prospex has the remaining 37% working interest.

Mark Routh, Prospex's CEO, commented:
'We are very pleased that all necessary approvals for gas production at Podere Maiar - 1 (PM-1) have been successfully obtained. Following the completion of thorough safety checks by UNMIG and the Fire Department and the final approvals by the Italian Energy Ministry, we are now poised to begin production from the PM-1 well on the Selva field.
'Regional flooding issues have delayed final approvals and production, but we can now say with confidence that we shall see gas production and cash flow from the asset in the near term. It is a credit to our partners at Po Valley Energy and their team on the ground, Po Valley Operations, who have persevered to make today's announcement possible.'