Petro Matad, the AIM quoted Mongolian oil company, has provided an operational update.

Key updates

  • Block XX acidisation operations completed at Heron-2. Well clean up continuing.
  • Workover rig mobilising to Gazelle-1 for well testing programme.

Well Testing Operations

As previously reported, activities to acidise and re-test the Heron-2 well commenced on 25 August. The well was re-entered and cleaned out by means of a swabbing operation which uses a tool run on wireline to lift fluid out of the well bore. During the pre-acid clean up gas and oil were observed in greater concentrations than those seen in the original well testing programme conducted in October 2024.

The acid wash programme was then completed successfully with the planned volume of acid injected into the reservoir. After a 20 hour soak the swabbing string was re-run to recover the injected fluid, clean out the hole and begin recovery of reservoir fluid. However, with 640 barrels of injected fluid still remaining to be recovered, the Company has now determined that the quickest and most cost-effective way to get a definitive result from the re-test of Heron-2 is to run a completion string, install a surface pump and conduct a pumped test.

Work has now started to complete the well and install temporary surface production equipment. PetroChina has provided us with a suitable second-hand beam pump and our construction contractor has mobilised to site. We expect to be ready to start pumping operations by month's end to recover the remainder of the injected fluids and then determine the flowing reservoir fluid and the well's productive capacity. Should a commercial oil rate be achieved the temporary facilities can continue to operate whilst a permanent storage tank is installed. PetroChina has identified a second-hand tank that we can use if required.

The workover rig is now moving to the Gazelle-1 well. All permits and approvals are in place to commence the well test programme which we anticipate will start before the end of September and complete by the end of October after which the rig will move to Gobi Bear-1.

Photo - see caption
Source: Petro Matad

Mike Buck, CEO of Petro Matad, said:

'The Heron-2 acid job went according to plan but taking into account the significant volume of unrecovered injected fluid in the well, completion and pumping offer a timely and cost-effective way to get a definitive result in this re-test. We are grateful to our neighbours PetroChina for providing equipment to enable us to adapt the Heron-2 programme expeditiously. We look forward to a smooth rig up at Gazelle-1 and to testing the well during October.'

Further operational updates will be provided in due course.

Original announcement link

Source: Petro Matad





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2933

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Merlin
Bayphase
energy365
Rose & Assocs
Telos NRG
OPC
Union Jack Oil 149
Borchwix
Syntillica
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com