Netherlands: Vattenfall and Copenhagen Infrastructure Partners award DEME contract for foundation installation at Zeevonk offshore wind farm


23 Jul 2026

Photo - see caption

Vattenfall and Copenhagen Infrastructure Partners (CIP), through their joint venture Zeevonk, have awarded a contract to DEME for the transport and installation of foundations for phase 1 of the Zeevonk offshore wind farm in the Dutch North Sea

Under the contract, DEME will be responsible for intermediate transport of monopiles, marshalling services for primary and secondary steel, plus transport and installation of 69 monopile foundations as well as the installation of a filter layer for scour protection. The project remains subject to a final investment decision. 

Felix Würtenberger, CEO of Zeevonk, said: 'Developing a project of this scale requires strong partnerships and deep offshore expertise. DEME has a proven track record in offshore wind and we are pleased to welcome them to Zeevonk. This contract marks another important milestone as we continue to advance the project and work towards delivering one of the Netherlands’ next large-scale offshore wind projects.'

Bas Nekeman, Business Unit Director Northern Europe at DEME, said: 'We are excited to build on our strong partnership with Vattenfall and Copenhagen Infrastructure Partners. The Netherlands continues to be a key market for offshore wind, and Zeevonk will play an important role in its further expansion. We look forward to contributing our expertise to the successful delivery of this project.' 

The works will be carried out using several vessels from DEME’s fleet, including the offshore installation vessel Orion for monopile installation, supported by a jack-up vessel for secondary steel and a fallpipe vessel for scour protection. 

About Zeevonk 

Covering an area of 650 sq km, the Zeevonk project will be located in front of the Dutch North Sea coast, between 63 and 84 km away from the coastal town of Bergen aan Zee. The project is divided in two stages. Phase 1 delivers 1 GW of offshore wind by 2029. Phase 2 follows in 2032, adding another 1 GW of wind and 500 MW of system integration capacity. This includes the development of an electrolyser in the Port of Rotterdam to enable green hydrogen production. Zeevonk is co-owned by Vattenfall and CIP through its Energy Transition Fund I.

Original announcement link

Source: Vattenfall





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2933

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Merlin
Rose & Assocs
OPC
Bayphase
Syntillica
Telos NRG
energy365
Borchwix
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com