Norway: Equinor reduces emissions from the Troll field


11 Sep 2024

Photo - see caption

On Saturday, 7 September, Troll B and C became partly powered from shore. This reduces annual emissions from the Norwegian continental shelf (NCS) by 250,000 tonnes of CO2.

This is in line with the plan for development and operation (PDO) for Troll West electrification (TWEL), which was approved by Norwegian authorities in 2021.

Photo - see caption
Equinor reduces emissions from the Troll field

Photo: The Troll C platform in the North Sea

'Troll B and C electrification marks an important milestone in the efforts to halve the emissions from our operations by 2030. The project reduces CO2 emissions by the equivalent of those from 125,000 fossil-fuelled cars,' says Geir Tungesvik, executive vice president for Projects, Drilling & Procurement.

The power to Troll B and C comes from Kollsnes, northwest of Bergen. From here it runs through a new electro building shared by the Troll and Oseberg fields out to Troll B in a 132 kV power cable, and from there to Troll C.

The project has installed new modules on Troll B and C that adjust the voltage to the systems on board. The processing systems and other energy-intensive systems on both platforms are now driven by electricity, except for the large export compressors, which are still gas-powered.

'Troll West electrification has generated substantial business activity for Norwegian suppliers. Over 70 percent of the investments in the project have gone to companies in Norway. I am very pleased that we, along with our partners and suppliers, have succeeded in executing the project in a safe and effective manner,' Tungesvik says.

The CO2 reduction is equivalent to about half a percent of Norway’s total annual emissions. NOx emissions from the field are also reduced by around 850 tonnes per year. Gas burned in turbines to provide energy on the platforms can now be exported and more efficiently used in Europe.

'We have made several new discoveries in the Troll and Fram area in recent years. Thanks to Troll B and C electrification we can develop and produce these resources with very low emissions. The Troll area will continue to deliver large volumes of low-carbon, high-value energy for many years to come,' says Kjetil Hove, Equinor’s executive vice president for Exploration & Production Norway.

The TWEL project is continuing to fully electrify the Troll C platform so that all power needs are met with electricity from land. The measure will cut annual emissions by another 200,000 tonnes of CO2. Overall, this will help cut almost four percent of the total emissions from oil and gas production, around one percent of total emissions in Norway.

Infrastructure at Kollsnes and the cable to the platform are designed for a possible future full electrification also of Troll B.

The Troll A platform (Troll East) was the first platform to be powered from shore on the NCS, and has been electrified since start-up in 1996.

Facts

  • The licensees in Troll Unit are Equinor 30.6% (operator), Petoro 56%, A/S Norske Shell 8.1%, TotalEnergies 3.7% and ConocoPhillips Skandinavia AS 1.6%.
  • Aker Solutions AS has built three electro modules at its Stord yard and been responsible for the procurement and installation of all electrical equipment in the modules and in the new electro building at Kollsnes.
  • In addition, Aker Solutions has been responsible for all modification work on Troll B and C and all hook-up to existing operating systems both offshore and at Kollsnes.
  • Heavy lifts of modules were performed by Heerema.
  • For the Kollsnes sub-project, the main supplier is Skanska Norge AS, responsible for constructing the transformer substation and landfall area.
  • Total investments in the project are NOK 8.1 billion.
  • Aker Solutions’ contract is worth about NOK 2.9 billion, generating about 1000 person-years (FTE) of employment.
  • The module fabrication took place at the Stord yard. Aker Solutions estimates that 4000 people were involved in the work.
  • NKT has been responsible for the production and installation of the power cable. NKT’s contract is worth NOK 1 billion. The cable production was carried out at NKT’s facility in Karlskrona, Sweden.
  • Skanska Norge AS’s contract is worth around NOK 370 million and generated about 100 person-years of work (FTE) for Skanska and sub-contractors in the project period.
  • The power demand for Troll B and C will be up to 116 MW after full electrification of Troll C.

Original announcement link

Source: Equinor





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2932

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Telos NRG
Bayphase
energy365
Borchwix
Rose & Assocs
Merlin
Union Jack Oil 149
Syntillica
OPC
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com