Trillion Energy on Feb 14 provided a progress update on the Guluc 2 and West Akcakoca 1 wells at the SASB Gas field, Black Sea Turkiye.

Guluc-2 is the third well in our multi-well program, which reached total depth (TD) on Jan 31 as previously announced in its February 2 news release. Trillion initially anticipated perforation and flow testing last week; however, completion has been temporarily delayed while the Company awaits delivery of well tools to allow the perforation guns to be properly conveyed and positioned into the well. Shipping issues due to the earthquakes caused delays in receiving certain tools, but the tools were expected late last week.
To avoid the rig standing idle waiting for tools, it has been skidded to the West Akcakcoa-1 well ('WA-1') (to which 1008 metres of surface hole was previously drilled late in 2022) which will now be drilled to TD. After drilling of WA-1 is complete, both WA-1 and Guluc-2 wells will be perforated for production.
Source: Trillion Energy