Zimbabwe: Invictus provides Mukuyu-2 drilling update


03 Oct 2023

Photo - see caption

HIGHLIGHTS

  • Surface hole section drilling completed to a depth of 496m
  • Exalo Rig 202 to drill intermediate hole section through the secondary targets
  • Mukuyu-2 on track to complete drilling and evaluation within estimated 50-60 days

Invictus Energy has announced an update of the drilling of the Mukuyu-2 well at its 80% owned and operated Cabora Bassa Project in Zimbabwe.

Progress

Since the last update, the Exalo Rig 202 has drilled the 17 ½” surface hole section down to a depth of approx. 496m Measured Depth ('MD').

The 13 3/8 inch casing has been set in place and the blow out preventer (BOP) stack successfully installed, with drilling of the intermediate 12 1/4 inch hole section commenced.

Forward Plan

Rig 202 will continue to drill ahead in the 12 1/4 inch intermediate hole section through the Dande and Forest targets to a planned total section depth of approx. 2,040m MD within the Pebbly Arkose formation before running a wireline logging evaluation suite and then setting the 9 5/8 inch casing.

After setting the 9 5/8 inch casing the rig will drill ahead in the 8 1/2 inch hole section through the reminder of the Pebbly Arkose through to the primary targets in the Upper Angwa (Alternations Member) and to the Lower Angwa (Massive Member) to approximately 3,750 metres MD before running a wireline logging evaluation suite.

Mukuyu-2 Well Objectives

Mukuyu-2 will be drilled to a planned total depth of 3,750 metres. Drilling and evaluation of the well is prognosed to take approx. 50 to 60 days to complete.

Mukuyu-2 will test the primary target interval, the Triassic Upper Angwa formation, sitting approximately 450m updip from Mukuyu-1 where hydrocarbons were intersected, as shown in Figure 2.

The well will also penetrate multiple additional targets including the Dande (Jurassic-Cretaceous), Forest and Pebbly Arkose (both Triassic) formations, as well as the previously untested Lower Angwa sequence within the Mukuyu anticline in the central horst structure, as shown in Figure 1 and Figure 2.

The Company will provide regular updates as the drilling campaign progresses.

Photo - see caption
Figure 1 - Mukuyu-2 to Mukuyu-1 correlation, well trajectory and primary targets
Photo - see caption
Figure 2 - Mukuyu-2 well schematic

Original announcement link

Source: Invictus Energy





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2932

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Syntillica
Union Jack Oil 149
OPC
Merlin
Rose & Assocs
Telos NRG
Borchwix
Bayphase
energy365
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com