Zimbabwe: Invictus Energy awards contracts for Musuma-1 exploration well - preparation for drilling commences


08 Jul 2026

HIGHLIGHTS

  • Wellpad construction and civils contracts awarded, including access road upgrades and water supply infrastructure for the Musuma-1 exploration well supporting the Company’s procurement schedule and Musuma-1 drilling readiness.
  • Exalo S.A. commencing in-country setup, rig maintenance activities and working with Invictus’ in-country team on rig move planning and execution.
  • Outstanding long-lead equipment suppliers including wellheads and tubulars have been evaluated and contract awards preparing to be made.
  • Evaluation of drilling & well services are advanced, with award of well services packages targeted in the coming weeks.
  • Logistics and mobilisation plan for services from neighbouring countries prepared, award to follow drilling well services contracts.
  • Company remains on track to spud high impact Musuma-1 in H2 2026.
Photo - see caption

Invictus Energy has announced the award of key contracts covering wellpad construction and civil works, and the mobilisation of logistics and support services, in preparation for the drilling of the Musuma-1 exploration well in the Cabora Bassa Project, Zimbabwe.

Wellpad construction and civils

Invictus has awarded contracts for the construction of the Musuma-1 wellpad and associated civil works. The scope of work includes upgrades to access roads required to support rig transport and ongoing operations, as well as establishing water supply infrastructure required for drilling operations. Site works are being planned to ensure the wellpad and associated infrastructure are ready to receive Rig 202 in line with the Company's planned drilling schedule.

Long lead items

The Company has completed the evaluation of long lead equipment suppliers required for the Musuma1 well and is preparing to make the award for supply of the remaining equipment. With these items now secured, all major long lead procurement for the well is in place.

Rig 202 critical maintenance and mobilisation

Exalo Drilling S.A, the contractor for Rig 202, is mobilising a team to Zimbabwe this week to commence in-country setup and commence the scope of work associated with critical maintenance on Rig 202.

This work is being undertaken in coordination with Invictus’ in-country team ahead of the planned rig move to the Musuma-1 wellpad and rig acceptance process in preparing the rig for the upcoming drilling campaign.

Well services provision

Evaluation of tenders for the provision of well services to support the Musuma-1 drilling campaign is well advanced. The Company anticipates awarding the well services contract in the coming weeks, completing the final suite of contracts required to support the well.

Logistics and mobilisation

The Company has prepared a logistics and mobilisation plan to support seamless mobilisation of services required to support the upcoming drilling campaign. This includes the coordination of equipment, materials and personnel movements into the field, ensuring operational readiness ahead of rig arrival at the Musuma-1 wellpad. The selection of logistics providers is being finalised with contract award expected following selection of drilling and well services provider(s).

Photo - see caption

Map Source: Invictus Energy

Invictus Managing Director Scott Macmillan commented:

'Awarding wellpad construction, civils, road upgrade, water supply, long-lead equipment and logistics contracts represents an important step in our preparations for the Musuma-1 exploration well. These allow us to move into the field execution phase and ensure the necessary infrastructure, equipment and mobilisation planning are in place ahead of drilling.

'Securing the remaining long-lead items, including wellheads and tubulars, is a key procurement milestone and supports our drilling readiness for the planned H2 2026 campaign.

'We are also pleased that Exalo S.A. is mobilising its team this week to commence in-country setup and critical maintenance activities for Rig 202 ahead of its planned move to the Musuma-1 wellpad.

'The evaluation of well services provision is well advanced, and we are targeting award of these remaining scopes in coming weeks. The Company remains on track to spud Musuma-1 in H2 2026.'

Musuma-1 exploration well spud on track for H2 2026

With wellpad construction, civils, logistics and rig maintenance activities progressing in parallel, Invictus remains on track to spud the Musuma-1 exploration well in H2 2026. Traditional and cultural ceremonies will be held at the Musuma-1 wellsite ahead of wellpad construction.

Musuma-1 is targeting an estimated gross mean unrisked prospective resource of 1.2 Tcf of gas and 73 million barrels of condensate# and represents one of the most significant undrilled conventional exploration opportunities in the Cabora Bassa Basin.

#Cautionary Statement: These estimated quantities of petroleum that may be potentially recovered by the application of a future development project relate to undiscovered accumulations. The estimates have both a risk of discovery and a risk of development. Further exploration, appraisal and evaluation are required to determine the existence of a significant quantity of potentially recoverable hydrocarbons. Prospective Resource assessments in this release were estimated using probabilistic methods in accordance with SPE-PRMS standards.

Musuma-1 has been confirmed as the first high-impact exploration well to be drilled outside the Mukuyu gas-condensate discovery area, targeting a new play type in the Cabora Bassa Basin. The well has the potential to unlock a substantial new resource base in the eastern portion of the licence area where several high potential prospects have been identified from the CB23 seismic survey.

Musuma-1 presents one of the strongest technical cases observed outside of Mukuyu and will be crucial to understanding the resource potential in the eastern portion of Invictus’s dominant acreage position.

Original announcement link

Source: Invictus Energy





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2933

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Borchwix
OPC
Syntillica
Merlin
energy365
Bayphase
Rose & Assocs
Telos NRG
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com