Vestas has announced two news orders from JUWI in Germany as part of its Q3 order intake.
The Mehring II project is 43 MW and comprises 7 x V162-6.2 MW turbines and a 20-year AOM 4000 Service Agreement. Delivery planned to begin in Q4 2027; commissioning scheduled to begin in Q2 2028.
The Breuberg project is 43 MW and comprises 7 x V162-6.2 MW turbines and a 20-year AOM 4000 Service Agreement. Delivery planned to begin in Q1 2028; commissioning scheduled to begin in Q3 2028
Source: Vestas