News listings

energy-pedia general news

Indonesia flagIndonesia

Central & SE Asia / Australasia >>> Indonesia

Indonesia: Conrad Asia Energy provides quarterly activities report for the period ending 31 December 2023


31 Jan 2024

Photo - see caption

Conrad Asia Energy, an ASX-listed Asia-focused natural gas exploration and development company, has provided an overview of activities for the quarter ending 31 December 2023.

  • Considerable progress has been made in maturing the Mako project during the past months. The key developments include:
    • Front end engineering design (“FEED”) studies for the Mako development project have concluded. Based on these studies (and the procurement process to date), capital costs for Phase 1 are currently estimated to be US$325 million1 based on a 100% participating interest,2 in line with market trends. Capital expenditures to initial revenues are currently estimated to be US$250 million(1) (100%). Project costs and expenditure scheduling are being further optimised to reduce this amount. The planned development wells are targeted to deliver 120 mmscfd (100%) for a plateau period of seven years(1).
    • In Q3 2023, the Company signed a non-binding term sheet (the “Term Sheet”) with Sembcorp Gas Pte Ltd (“Sembcorp”), a major Singapore energy company, which outlines the core terms and serves as the basis for negotiating a definitive Gas Sales Agreement (“GSA”). Subsequent commercial negotiation between the Minister of Mining and Natural Resources and Sembcorp has resulted in both improved price formula and a delay in executing the GSA, and accordingly, Conrad has agreed with Sembcorp to delay the deadline to finalise a binding GSA (which will be subject to customary conditions precedent) by the end of Q2 2024.
    • During the quarter, Conrad progressed the technical and commercial work with the West Natuna Transportation System (“WNTS”) Joint Venture and with the support of SKK Migas to negotiate the commercial and legal terms of access to the WNTS for the transportation of the Mako gas to Singapore. Despite the good progress, delays have been encountered and this has required a revision of the project timeline and finalisation of the GSA.
  • While the Company continues to strive to reach a Mako final investment decision (“FID”) at the earliest, on the current trajectory of conclusion of the GSA and gas transportation agreement, FID would be delayed until mid-2024. Production start-up would commensurately slip until mid-2026.
  • The Duyung farm down process is progressing. With the announcement of the Term Sheet, as well as progress on all other facets of the project, more parties have expressed interest in the Mako project. The Company is engaging in confidential discussions with potential partners regarding acquisition of a Participating Interest in the Duyung PSC.
  • Conrad has appointed a financial advisor to assist with the debt funding portion of its share of the Mako project capital cost. Conrad has received an indicative term-sheet from one of the potential lenders to help fund Conrad’s share of project costs. Lender selection and completion of documentation are expected by mid-2024.
  • In the Aceh Production Sharing Contracts ("PSCs"), Conrad has continued to evaluate options for commercialisation of shallow-water gas discoveries with gross (100%) 2C Contingent Resource of 214 Bcf of sales gas (161 Bcf net attributable to Conrad) in three of the four discovered gas accumulations(3). An update to the market is expected in the coming weeks. The Competent Persons Reports (“CPRs”) (3) ascribed a net present value (“NPV”) of US$88 million net attributable to Conrad to the Aceh PSCs.
  • Prospective Resources in the Aceh PSCs are in excess of 15 trillion cubic feet (“Tcf”) of recoverable gas (P50, 100%) of which c 11 Tcf (P50) are net attributable4 to Conrad5. Seismic studies revealed the presence of direct hydrocarbon indicators (“DHIs”) including gas chimneys at many of the leads. The Company has been approached by potential partners seeking material gas exploration opportunities. Recent multi-Tcf gas discoveries made elsewhere in offshore Aceh have highlighted the potential of this region.

Conrad Managing Director and Chief Executive Officer, Miltos Xynogalas, commented:

'Conrad has made solid progress with the Mako development project in the fourth quarter despite the delay in FID caused by extended negotiations with the WNTS stakeholders. The completion of the FEED studies and the progression of the environmental impact assessment (AMDAL) are significant milestones. The target of the end of Q2 2024 to finalise the GSA is a clearly defined target shared by all parties. The time taken to conclude negotiations has allowed an agreement in principle of improved price terms and has provided an opportunity to further optimise the amount and phasing of Phase 1 capital expenditures, significantly reducing cash required through initial gas production.

The response of potential debt finance providers and potential farminees is encouraging, and we have seen increased interest in the region to fund gas developments. We remain confident that when all commercial aspects of the project have been concluded, Conrad will be in a position to take FID. The optimised capital expenditures (via a staged production start-up) into an expected higher gas pricing regime delivers robust project economics. The extended timeline also allows more time for the company to advance current negotiations and to engage with other potential farm-in partners. Our goal is to continue to maximise economic returns to shareholders.

Significant progress has also been made in Conrad’s Aceh project area with the resource certification of existing discoveries(3) that are currently being evaluated for commerciality, as well as our announcement(3) of the size of the prospective resources (15 Tcf gross 100%). During the coming weeks, Conrad will seek to progress the potential market outlets for the existing flow-tested shallow water discoveries with the aim of maturing this into another significant gas project for Conrad. Commercialisation of the shallow water discoveries will increase Conrad’s 2C contingent resources by 75%.

We have seen offshore Aceh increasingly becoming an area of greater exploration focus, with major discoveries of multi-Tcf potential being announced late in 2023. Conrad has approximately 20,000 sq km acreage in offshore Aceh and is well positioned to participate in the development of its existing shallow water discoveries and pursue the deeper water high impact exploration where large structures have already been delineated.'

Original announcement link

Source: Conrad Asia Energy





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 237

Completed Deals

Completed Upstream Deals: 6558

Company Profiles

Current Company Profiles: 2912

Corporate Activity

Current Corporate Activity articles: 4136

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1653

Geostudies

Current Geostudies articles: 964

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Union Jack Oil 149
Syntillica
Bayphase
Borchwix
OPC
energy365
Merlin
Rose & Assocs
Telos NRG
Government of South Australia
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com