Poland: Equinor announces financial close for Baltyk 2 and Baltyk 3


23 May 2025

Photo - see caption

The project joint venture partners Equinor (50%) and Polenergia (50%) have reached financial close for the Baltyk 2 and Baltyk 3 projects. Two project financing packages of over EUR 3 billion for Baltyk 2 and over EUR 3 billion for Baltyk 3 including ancillary facilities, have been secured.

The offshore wind projects were awarded Contracts for Difference (CfD) in 2021, securing power prices at approximately EUR 71 per MWh (2021 price) for 25 years, with inflation indexation. The wind farms are project financed with gearing of approximately 80%. The projects support Equinor’s expected double-digit nominal equity rate of return for renewables and low carbon investments.

Equinor is responsible for the construction phase and will be the operator of the two offshore wind farms. Onshore construction work is ongoing, fabrication of key components has started, while marine operations will start next year. Total power capacity of the projects is 1440 MW, enough to power 2 million Polish homes. Full commercial power production is expected in 2028. The individual project finance packages will fund the capital investment and the other expenses of each of the projects during the construction process totaling approximately EUR 7.2 billion.

Danske Commodities, an Equinor subsidiary, will provide route-to-market services including balancing and power offtake for the first three years of operations.

Following strong interest from lenders, Baltyk 2 and Baltyk 3 have secured competitive terms and conditions. The final group, comprising of around 30 financial institutions, includes the most experienced in the sector along with many of Equinor’s core banks, the Nordic Investment Bank and the European Investment Bank.

Final investment decisions for Baltyk 2 and Baltyk 3 were taken by the project joint venture partners, 19 May.

Senior vice president for Renewables in Europe, Trine Borum Bojsen:

'Building a profitable renewables business through safe execution and operations is key to delivering on Equinor’s strategy. With financial close reached for Baltyk 2 and Baltyk 3, the last important milestone is passed ahead of full-scale construction. We appreciate the strong interest and support from lenders. This underpins the attractiveness of the projects and the confidence in Polenergia and Equinor as developers.'

Country Manager in Poland, Michal Jerzy Kolodziejczyk:

'Baltyk 2 and Baltyk 3 represent the beginning of a new era in Poland's offshore wind energy development. These wind farms are set to contribute to Poland's industrial future by producing renewable electricity for Polish households, creating employment opportunities, and enhancing both energy security and the energy transition. We will collaborate with industry partners to ensure their delivery is safe and efficient.'

Photo - see caption
Equinor announces financial close for Baltyk 2 and Baltyk 3

Map Source: Equinor

About Baltyk 2 and Baltyk 3

Baltyk 2 and Baltyk 3, developed by Equinor (50%) and Polenergia (50%), the largest private energy group in Poland, are two offshore wind projects with a total capacity of 1440 MW (720 MW each). The two wind farms, developed in parallel, largely within the same time schedule, will consist of 100 fixed bottom turbines, placed 22-37 km off the Polish coast. All key suppliers have been selected and contracted and are among the most experienced in the industry. The operations and maintenance base will be situated in Leba, located in the region of Gdansk in northern Poland. The base will serve as a centre for marine operations and support during the construction phase. Equinor is the owner of the base and will be the operator of the projects.

Original announcement link

Source: Equinor





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2932

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Borchwix
Merlin
Telos NRG
OPC
Rose & Assocs
energy365
Syntillica
Union Jack Oil 149
Bayphase
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com