News listings

energy-pedia development and production

Spain flagSpain

Europe / Caspian / CIS >>> Spain

Spain: Rental of transformer at El Romeral enables production re-start


22 Jan 2026

Photo - see caption

Prospex Energy, the AIM quoted investment company focused on European gas and power projects, has announced that Tarba Energía has signed a contract for the rental of a transformer at the El Romeral gas to power plant in Andalucía, Spain, enabling the plant to resume electricity generation and sales.

The transformer is to be delivered on site and installed before the end of January 2026.  The rental transformer will be on contract until the delivery of the new electricity transformer which was ordered from a supplier in Spain last November.  Tarba is in dialogue with that supplier on the progress of the new build.

Mark Routh, Prospex's CEO, commented:

'The Company is pleased to have sourced a rental transformer for the El Romeral plant.  The transformer, which has an almost unique voltage and power specification is expected to be installed this week allowing Tarba to resume the production of electricity before the end of January.

'We remain confident in the value and development potential of the El Romeral asset and are pleased that the permitting to drill five new natural gas wells is in its final stages.

'The El Romeral power plant can reach full capacity from production from just two of the proposed five new wells.  Any extra gas from the remaining new wells or any future wells drilled on the concessions will support expansion plans at the power plant as well as the ability to supply natural gas directly to the gas grid.  The El Romeral concessions have substantial development potential with more than 90 bcf of gas[1] now owned 100% by Prospex.

'We will continue to keep shareholders updated on the permitting process.  Since we are now in the final stage of receiving the permits to drill these five wells, we have started the process of optimising the funding of the wells by seeking potential debt funding and farm-in partners.'

Rental Transformer Contract

Tarba has been unable to procure a rental transformer which fits the almost unique voltage and power specifications required to meet the export requirements to deliver electricity from Tarba's gas engine generators to the high voltage grid connection.  Therefore, as reported in the RNS of 17 November 2025, in mid-November 2025 Tarba ordered a brand-new transformer, which is estimated to be delivered by Q3 2026.  This new rental transformer has been procured from the same contractor that rented a transformer to Tarba in February 2025.  As previously reported, that company asked to replace the original transformer with a smaller unit at a reduced rental cost on 1 July 2025, but owing to unforeseen events the replacement transformer was not delivered as agreed, resulting in the cessation of production and gas generation at Tarba's El Romeral plant since that date.  A claim for compensation for lost production was agreed but that claim was subsequently referred to the rental company's lawyers and payment did not occur.  In order to sign an agreement for the immediate supply of the new rental transformer, Tarba has had to waive its €76,000 claim for compensation.  This however will allow the resumption of production and sales at El Romeral as soon as possible.  Tarba took the decision that the legal costs and time required to pursue the claim in the Spanish legal system would outweigh the value of the claim and further delay resumption of production. 

Tarba sells its generated electricity on the spot market and prices can vary hugely each day and within day on account of solar power and wind turbine power dominating the markets.  Recent within day electricity prices have been recorded between €0/MWh at midday and more than €200/MWh in the nighttime hours.  It is Tarba's intention to generate electricity from the remaining gas reserves in El Romeral during the overnight hours when prices exceed €100/MWh.

5-Well drilling Permitting Process

As advised in the RNS of 17 November 2025, the full suite of Environmental Impact Assessment ("EIA") documentation for the application by Tarba to drill five new natural gas wells on the El Romeral concessions was submitted to The Ministry for the Ecological Transition and the Demographic Challenge in Madrid ("MITECO") on Friday 14 November 2025.  That documentation was forwarded internally to the to MITECO's Environmental Department 5 December 2025.  MITECO's timeline for this final step of the approvals process is 90-180 days.

The El Romeral concessions, now 100% owned by the Company through Tarba, has an identified resource base of more than 90 bcf[1] of gas.  The five wells being permitted are targeting the lowest risk structures in the concessions with best estimate contingent and prospective gas resources of 18.2 bcf.

Seismicity Study

In December 2025, Tarba completed a project to record the background seismicity across the three El Romeral concessions in order to establish the background seismicity of the area.  This step is a recommendation (but not a requirement) from the EIA process so that Tarba can demonstrate to the regulators that any future extraction of natural gas from the concession areas does not cause a seismic event.

Background on El Romeral

Tarba generates electricity at its El Romeral power plant from its own natural gas production from the concessions, which in July 2024 were granted a ten-year extension by MITECO to July 2034.  The five wells are planned to target the five optimum structures on the El Romeral concessions, which will produce biogenic gas from shallow subsurface horizons.  The depth of the wells average about 700 metres and will each take no longer than 3 to 4 weeks to drill once a suitable drilling rig has been mobilised after the well permits are secured.

Original announcement link

Source: Prospex Energy





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2933

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Borchwix
Rose & Assocs
Bayphase
Union Jack Oil 149
Telos NRG
energy365
OPC
Merlin
Syntillica
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com