Trinidad: Touchstone provides update on Cascadura facility


27 Feb 2023

Photo - see caption

Touchstone Exploration reports that on February 24, 2023, the Company was notified by The National Gas Company of Trinidad and Tobago ('NGC') that they expect to be ready to receive first gas from the Cascadura natural gas and associated liquids facility on or about June 30, 2023.

Touchstone remains on track to complete the Cascadura facility prior to this date to ensure production can commence as soon as NGC is in a position to receive first gas. The approximate construction status of the Cascadura facility is as follows:

  • the civil and concrete foundation work for the main process facility equipment is complete;
  • the flare stack is procured, with the associated foundation work commencing imminently;
  • the communication tower is approximately 80 percent complete;
  • the pipe racks are approximately 90 percent assembled with hydrotesting initiated, and the units are expected to arrive at the facility within the next three weeks;
  • on-site condensate tanks are approximately 65 percent complete;
  • the compressors, separators, and vapour recovery units have been safely transported to the facility; and
  • all process equipment for the facility has been acquired.
Photo - see caption
Touchstone Exploration has been notified by The National Gas Company of Trinidad and Tobago that they expect to be ready to receive first gas from the Cascadura natural gas and associated liquids facility on or about June 30, 2023.

Paul Baay, President and Chief Executive Officer, commented:

'We are encouraged to have received an expected first gas date from NGC. Although this is later than we were anticipating, we can now plan the final phase of our various work streams to minimize costs and optimize services.

First gas from Cascadura will be a transformative achievement for Touchstone, and we thank shareholders for their continued support and patience as we work towards this significant milestone.  

We expect that the funds raised late last year and our current base production will allow us to complete drilling the Royston-1X well and prepare our next development locations at Cascadura while we finalize construction of the Cascadura facility.'

Original article link

Source: Touchstone Exploration





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 237

Completed Deals

Completed Upstream Deals: 6558

Company Profiles

Current Company Profiles: 2912

Corporate Activity

Current Corporate Activity articles: 4135

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1653

Geostudies

Current Geostudies articles: 964

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

OPC
Union Jack Oil 149
Telos NRG
Borchwix
Rose & Assocs
Syntillica
Merlin
Government of South Australia
energy365
Bayphase
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com