UK: RWE celebrates next milestone for Sofia offshore wind farm, with installation of first turbine


31 Mar 2025

  • Turbine installation vessel Wind Peak will install all Sofia’s turbines, carrying components for six turbines per sail-out.
  • Half of the turbine blades on the Sofia project are recyclable.
  • Sofia’s 100 turbines will stand 252m tall, taller than the buildings at Canary Wharf.
Photo - see caption

RWE, one of the world’s leading offshore wind companies, has announced that the first turbine has been successfully installed at its Sofia Offshore Wind Farm. This important milestone marks a key moment in the construction of one of RWE’s largest and most powerful wind farms.

The turbine installation vessel, Wind Peak, from Cadeler, arrived at the offshore site for the first time during the weekend of 22 March, where it started and has now completed the installation of the first turbine. During each vessel cycle, the Wind Peak will carry and install six sets of the latest SG 14-222 wind turbines, supplied by Siemens Gamesa.

Photo - see caption

Thomas Michel, COO RWE Offshore Wind said: 'This is yet another great construction milestone for Sofia, one of RWE’s flagship offshore wind farms in the UK. The team and our contractors are making great progress with the construction work both onshore and offshore. We’re now looking forward to Sofia making a significant contribution to the UK’s Clean Power 2030 targets, after commissioning, which is expected in 2026.'

The Sofia Offshore Wind Farm will comprise 100 Siemens Gamesa 14MW turbines, making it one of the largest single offshore wind farms in the world. Sofia will generate enough renewable energy to power the equivalent of up to 1.2m typical UK homes. It is on course to be fully operational in the second half of 2026.  The turbines are the engine room of RWE’s 1.4 gigawatts offshore wind farm. Each one stands over 252 metres above sea level, with blades of 108 metre sweeping an area of 39,000 square metres, which is equivalent to about 5.5 standard UK football pitches.

In a step forward for the offshore wind sector, half of the turbine blades to be installed on the Sofia project will be recyclable. This represents a pioneering step toward full lifecycle sustainability for an offshore wind farm and aligns with RWE’s sustainability ambitions.

Original announcement link

Source: RWE





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2933

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Bayphase
Telos NRG
Merlin
Syntillica
Union Jack Oil 149
Rose & Assocs
OPC
energy365
Borchwix
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com