News listings

energy-pedia alternative energy

Tanzania flagTanzania

Middle East / Africa >>> Tanzania

Tanzania: Helium One Global announces Southern Rukwa Project update


16 Feb 2026

ESP Testing Demonstrates Enhanced Flow Rates and Supports Strategic Farmout Process

Photo - see caption

Helium One Global, the primary helium explorer in Tanzania with a 50% working interest in the Galactica-Pegasus helium development project in Colorado, USA, provides the following update on the southern Rukwa Helium Project.

 Highlights 

  • Successful completion of Electrical Submersible Pump ("ESP") testing at ITW-1 at the southern Rukwa Helium Project with zero Lost Time Injuries
  • Produced over the equivalent of 250,000 barrels ("bbl") of water over a testing period of 20 days, with flow rates of up to an equivalent of 16,400 barrels per day ("bpd") - a six-fold increase in flow rate, compared with natural flow during the 2024 Extended Well Test ("EWT")
  • Sustained helium concentrations of 5.4% (air corrected) with a maximum concentration of 9.2% (air corrected) at surface
  • Sustained average measured gas water ratio ("GWR") readings of 0.06 m3/m3 (0.05 Sm3/Sm3 corrected for stp1) with a peak of 0.1 m3/m3 (0.08 Sm3/Sm3 corrected for stp1) during the continuous flow period
  • Downhole temperature measurements and salinities suggest mixing from both Basement sourced fluids and a Karoo Group aquifer
  • Upon shut in, the wellhead pressure and downhole pressure quickly re-pressurised indicating encouraging reservoir support
  • Strategic farmout process to commence to identify and select a suitable industry partner
Photo - see caption

 James Smith, Chairman, commented:

'The successful completion of the ESP testing programme represents an important operational milestone for Helium One and further demonstrates the production potential of the southern Rukwa Helium Project.

The testing delivered consistent and reliable operational performance, with ESP flow rates exceeding expectations and sustained helium concentrations in line with anticipated ranges. Whilst the gas water ratio was towards the lower end of the expected outcome range, the results provide valuable technical insight and further support the Company's understanding of the subsurface system.

Importantly, the operational success of this programme provides a strong foundation for the Company to progress discussions with potential industry partners and seek external investment to advance the project towards development. The Company intends to commence this process imminently.

The Board looks forward to updating shareholders as the Company continues to advance the southern Rukwa Helium Project towards commercial development.'

 Lorna Blaisse, Chief Executive Officer, commented:

'The ESP has effectively demonstrated that we can produce over 16,000 bpd and maintain consistent levels of helium concentrations over an extended period of time whilst managing the water disposal at surface.

We now need to increase our understanding of the Basement fault and fracture play, where we believe there is the potential to increase GWRs and helium concentrations. In order to do this, a further work programme will be required, and we will commence a strategic farmout process to seek an industry partner to help us deliver this.

I would like to thank the teams for all their efforts during this operational phase and extend my thanks to the local communities for their ongoing support of this project. The Company would also like to thank the Ministry of Minerals and the Mining Commission in Tanzania for their ongoing support.'

Details of ESP Testing

The Company has successfully completed the ESP testing programme at the ITW-1 well in southern Rukwa, and results from this testing programme provide key operational and technical data required to advance the project.

Following final downhole function checks and setup of surface equipment, the testing period commenced on 26 January, 2026 and was completed on 14 February, 2026.  The ESP equipment was provided and operated by CenerTech Group, part of the Chinese National Offshore Oil Company (CNOOC) and was operated for over 450 hrs with zero maintenance or downtime. Equipment and personnel are now being demobilised.

The well flowed at rates of up to the equivalent of 16,400 bpd with an average flow rate of 15,000 bpd on a maximum pump frequency of 55 Hertz. The ESP has successfully demonstrated a six-fold increase in flow rate, compared with natural flow during the 2024 EWT, with sustained levels of helium concentrations at surface.

Sustained GWR measurements averaged 0.06 m3/m3 (0.05 Sm3/Sm3 corrected for stp1) at 5.4% helium with a peak reading of 0.1 m3/m3 (0.08 Sm3/Sm3 corrected for stp1) during the continuous flow period.  The GWR used in the P90 case in the independent Competent Persons Report, that was completed in June 2025, was 0.04 Sm3/Sm3 with helium assumed to be 3.3%.

Temperature and salinity measurements recorded during the ESP test suggests that there may have been a higher contribution of shallower fluids from the Karoo aquifer which could have lowered the overall GWR and helium concentration.

The ESP was set 1,061m measured depth ("MD") within the fractured Basement, which was the lowest point at which the ESP could be set in open hole at the time of running in. This depth was slightly shallower than planned due to open hole ledges and the pump was positioned at the upper end of the primary Basement target. A packer was set in the lowermost Karoo Group at 840m MD to reduce comingled flow, but due to the nature of the high NtG2 and connectivity in the Karoo reservoir, the data suggests that isolation of Basement was not fully achieved.

During the testing period, the well produced a sustained average concentration of 5.4% helium (air corrected), with a peak of 9.2% helium (air corrected). The helium appears to be transported to surface primarily within fluids that were consistently measured at 90°C. This suggests dilution from the Karoo aquifer as pure Basement-derived fluids would have presented hotter temperatures at this depth, based on the known geothermal gradient for this area on the Itumbula High.

In addition to the temperature readings, the Company has also measured lower than expected salinity readings from the produced water - both from onsite testing and third-party laboratory testing in Tanzania. These values also support the rationale of an element of dilution from the younger Karoo aquifer, which has likely impacted the GWR measurements.

During the final stages of testing, the well was shut in and pressure measurements taken. During these tests, it was observed that the wellhead pressure and downhole pressure quickly re-pressurised which indicates encouraging reservoir support and the likelihood of a wider connected resource.

The ESP produced more than the equivalent of 250,000 bbl of water, a six-fold increase in flow rate compared with natural flow during the 2024 EWT, with no loss of helium concentrations. One of the concerns ahead of the ESP operation was water disposal at surface, which was carefully managed and subsequently did not impact the testing phase.  Going forward, this enables the Company to re-evaluate future water disposal options.

Forward Plan

The Company will now continue to evaluate the results of this test. In particular, it will seek to increase its understanding of the sources and interaction of the helium enriched fluids that have been identified. This will require further drilling and testing, which will likely focus on primary fractured Basement targets at other locations across the 480 km2 Mining Licence area. A number of these targets have already been identified by the Company, and many of these are at shallower depths where the Basement is juxtaposed against faults.

During this evaluative phase, the Company will also consider additional data acquisition options which will enable a more detailed evaluation of Basement fractures and connectivity. Future work programmes will need to focus on appraising the full potential of the Basement helium play.

In order to assist with further trajectory towards development of the southern Rukwa Helium Project, the Company believes that now is an appropriate time to seek third party financing. To this extent, the Company will now embark upon a formal farmout process that will identify and select a suitable industry partner.

Definitions

1stp Standard temperature and pressure conditions. Refers to the nominal conditions in the atmosphere at sea level. These conditions are 15 degrees Celsius and 1 atmosphere (atm) of pressure

2NtG Net to Gross is the measurement of clean, porous, and permeable reservoirs. High values suggest lack of seals and impermeable layers

Original announcement link

Source: Helium One Global





Bookmark and Share


A global information service for upstream oil and gas opportunities - divestitures, farmins and farmouts and licensing rounds.


Subscriber Only Deals

Current Deals

Current Upstream Deals: 195

Completed Deals

Completed Upstream Deals: 6640

Company Profiles

Current Company Profiles: 2933

Corporate Activity

Current Corporate Activity articles: 4197

Companies Looking

Current number of articles: 466

Company Sales

Current Company Sales articles:1674

Geostudies

Current Geostudies articles: 1003

How to subscribe

energy-pedia Jobs

RSS Feed Widget
See all jobs...


energy-pedia Databank

The energy-pedia databank contains links to information on the world financial and energy markets, including share prices, oil and gas prices and the global stock exchanges. Read more...



energy-pedia Glossary

A list of commonly used terms in the oil and gas industry. Read more...

Subscribe

Subscribe to the FREE
energy-pedia Daily Newsletter
Subscribe

Merlin
Union Jack Oil 149
OPC
Syntillica
Telos NRG
Bayphase
Borchwix
Rose & Assocs
energy365
About energy-pedia

energy-pedia news is a FREE news service written and edited by E and P professionals for E and P professionals.

We don't just report the news, we give you the technical background as well, with additional information derived from our unique energy-pedia opportunities service.
Contact us

energy365 Ltd

238 High Street
London Colney
St Albans
UNITED KINGDOM

Tel: +44(0)1727 822675

Email: info@energy-pedia.com